Prime Data Center NewsMarietta City Council approves Data Center near Delk Road and I-75At its packed meeting on August 12, 2026, the Marietta City Council approved a revised application for a data center at 1155 Powers Ferry Place, which is near Delk Road and I-75. This property is in the City of Marietta, but is also within the western border of the Powers Ferry Corridor, so we have been following the application closely, including attending City Council meetings.
(Note: This application was in progress before the Council enacted a data center moratorium that is set to end Dec. 31, 2026.) This will be an 18 MW data center, occupying about half of the existing Prime Storage warehouse. It is designated as “mission critical” to deliver the low-latency response that hospitals, emergency services, and public safety need. The proposal was first in front of the Marietta City Council on July 8th, but it was tabled until August 12th, so council members could study it further and so the applicant could provide more detailed information on key questions:
The City Council meeting on August 12th was a full house. When the data center came up for review, equal time was allotted to speakers for and against the application. Following the citizen input, Council members conducted a lengthy question and answer session with the applicant's team, which included multiple specialized engineers who provided very detailed information. The City Council's approval is based on the many stipulations added to the application. The detailed application documents can be viewed here on pages 16 to 82. Use the link below to watch the meeting video. The data center section covers almost two hours from 1:06:00 to 3:02:00. Video on City of Marietta website Read more in East Cobb News. |
Sign up for email updates on the Powers Ferry Corridor.
Data Center moratorium in the city of Marietta Through december 31, 2026Of note, the Prime Data Center is not subject to the moratorium, because it had filed for approval before the moratorium was passed by Marietta City Council on August 12, 2026. No other data centers will be considered in the City of Marietta until December 31st at the earliest.
Related to this move by the City of Marietta, it should be noted that Unincorporated Cobb County has its own separate code for data centers. The Cobb County Board of Commissioners has proposed extensive amendments to that code. Learn about these proposed changes on the Code Amendments page.
The Prime Data Center will be built in the existing Prime Storage FacilityThe data center will be built out as part of the existing Prime Storage facility. Approximately half of the warehouse building will be used, with equipment occupying part of interior and roof. Extensive sound mitigation will be installed, including a specially designed fence.
|
|
|